Installing a DEFINITY ECS ATM-PNC
3-1Equipment Installation
3
DEFINITY ECS Release 8.2 ATM Installation,
Upgrades, and Administration
555-233-124
Issue 1
April 2000
3
Installing a DEFINITY ECS
AT M -P N C
This chapter describes the procedures for installing a new DEFINITY ECS
Release 8 ATM system. The process includes
■ Equipment Installation
■ Synchronization Installation and Testing
■ ATM Network Duplication
Equipment Installation
If the ATM switch and interface circuit packs are already installed, then the actual
upgrade to ATM-PNC is done administratively in
Chapter 5, ‘‘Administering
ATM-PNC and ATM-CES’’.
To prepare for a new DEFINITY ECS ATM installation refer to the following books:
■ DEFINITY Enterprise Communications Server Release 8 Installation and
Test for Multicarrier Cabinets
■ DEFINITY Enterprise Communications Server Release 8 Installation and
Test for Single-Carrier Cabinets
Review the reliability configurations for DEFINITY Release 8 ATM (refer to
Figure
1-2 through Figure 1-4) and determine the synchronization sources (DS1, E1, or
ATM network).