ND-71548 (E) CHAPTER 3
Page 189
Issue 2
INSTALLATION PROCEDURE
NAP-200-013
Sheet 3/13
Cable Running from the PBX to MDF,
ATTCON, MAT, and SMDR
Cables for ODT Connectors Referring to description of 8TLT card in the
Circuit Card Manual, connect each 2400
ODT CABLE/2400 ODT CABLE-A and the
corresponding installation cables.
At the PBX side, bring each 2400 ODT
CABLE/2400 ODT CABLE-A up to the
connector position on the front of the 8TLT
cards to be mounted in the PIM.
At the MDF side, confirm the location of the
Terminal Blocks to which each cable is to be
terminated, then bring the cables up to the
terminal blocks.
END
A