NEC 2400 ipx Network Router User Manual


 
CHAPTER 5 ND-71548 (E)
Page 340
Issue 2
INSTALLATION TEST PROCEDURE
NAP-200-035
Sheet 1/1
SND (RST Card) Connection Test
START
When a C.O. Line or Tie Line is
not connected with the trunk,
make an arrangement for trunk
loop-back as illustrated above.
On the MDF, make temporary cross connections for a
loop back circuit.
Temporarily assign Office Data from the MAT so that a
connection can be set up with Station B via a SND.
Make busy all SNDs On the front of the RST circuit card, set all MBS switches
(0-7) to the OFF position, thereby making all SNDs busy.
Test SNDs one after another Un-busy (make idle) only the SND to be tested.
Station A dials the access code of the trunk and the
station number of Station B.
Station B answers and talks
The call is released.
Restore the temporary cross connections, temporary Office Data etc. to original configuration.
END
Station B
LC
LC
Station A
COT
LC
SND
ORT
MAT