INSTALLATION TEST PROCEDURE
NAP-200-036
Sheet 1/1
3-party Conference Trunk Function Test
START
Made busy all CFTs Made busy all CFTs using MAT command “MBTK”.
Test CFTs one at a time Un-busy (make idle) only CFT to be tested.
Stations A and B are engaged in a station to station connection.
Station A makes a Switch Hook Flash (SHF) and after hearing
DT, dials the station number of Station C.
Station C answers the call.
Station A, after having talked with Station C, makes a SHF and
confirms that a three-way connection has been set up.
The call is released.
Cancel the Make Busy of
the CFT
Un-busy (make idle) CFT using the “MBTK” command.
END