NEC 2400 ipx Network Router User Manual


 
CHAPTER 5 ND-71548 (E)
Page 362
Issue 2
INSTALLATION TEST PROCEDURE
6. IP CONNECTION TEST
6.1 Outline
Connection tests are to be performed to check IP connection by connecting terminals to the trunks and verify
the normality of the system. FCCS stands for Fusion Call Control Signaling.
6.2 IP Connection Test Procedure
The procedures for the IP connection test are described in the NAPs at the right of each item in the following
flowchart.
START
IP PAD Connection Test:
(IP PAD Card)
NAP-200-050
IPTRK Connection Test:
(IP Trunk Card for FCCS)
NAP-200-051
IPTRK Connection Test:
(IP Trunk Card for CCIS)
NAP-200-052
IPTRK Connection Test:
(IP Trunk Card for H.323)
NAP-200-053
PHA Connection Test:
(PHA Card)
NAP-200-054
PHD Connection Test:
(PHD Card)
NAP-200-055
PHC Connection Test:
(PHC Card)
NAP-200-056
END