Site Preparation
This section describes the steps to take and the considerations you should keep in mind prior to installing
an MGX 8230 chassis in a rack. It also contains information that applies to an MGX 8230 installation in
a Cisco closed rack. If the MGX 8230 arrives in a Cisco closed rack, your initial concerns would be the
cabinet grounding, and power connections.
For specifications on the enclosure and power system, see the Appendix A, Technical Specifications.
The topics and section names in this chapter are:
Site Preparation, page 3-1
Regulatory Compliance and Safety Information, page 3-3
Maintaining Safety with Electricity, page 3-3
Seismic Considerations, page 3-14
Seismic Anchoring for a Cisco Rack, page 3-14
Power and Grounding, page 3-17
Making the Frame Bonding (Ground) Connection, page 3-21
Parts Checklist
Before proceeding with the installation, verify that all the ordered parts are present and in good
condition. Store a record of the parts and serial numbers. If any parts are missing or damaged, contact
your sales representative.
Site Preparation
The site must satisfy the requirements in the following categories:
Space
The MGX 8230 IP + ATM Edge Concentrator is typically co-located in a rack with either an MGX
switch or a BPX switch.
Refer to the Cisco BPX 8600 Series Installation and Configuration documents for information about
rack and cabinet mounted switches.
Environment
The operating environment should be as follows: