Table 25: Site Preparation Checklist (continued)
DatePerformed ByFor More InformationItemor Task
“RackRequirementsforEX3200and
EX4200Switches” on page93
“CabinetRequirements forEX3200
and EX4200Switches” on page94
Verifythat yourrackor cabinet meetsthe
minimum requirements forthe installation of
the switch.
“ClearanceRequirementsfor Airflow
and Hardware Maintenance for
EX3200 and EX4200Switches” on
page 96
Planrackorcabinetlocation,includingrequired
spaceclearances.
Secure the rackor cabinetto the floorand
buildingstructure.
Wall
“Requirementsfor Mounting an
EX3200 or EX4200Switchon a
Desktop or Wall” on page95
Verifythat the wallmeets the minimum
requirements forthe installation of the switch.
“ClearanceRequirementsfor Airflow
and Hardware Maintenance for
EX3200 and EX4200Switches” on
page 96
Verifythatthereisappropriateclearanceinyour
selectedlocation.
Cables
Acquirecablesand connectors:
Determinethe number of cables needed
based on your planned configuration.
Reviewthe maximum distanceallowed for
eachcable.Choosethelengthofcablebased
on the distance betweenthe hardware
componentsbeing connected.
Planthe cableroutingand management.
Related Topics General Safety Guidelines and Warnings for EX Series Switches on page 207
General Site Guidelines for EX Series Switches on page 89
Installing and Connecting an EX3200 or EX4200 Switch on page 117
Mounting an EX3200 or EX4200 Switch on page 120
Copyright ©2010,Juniper Networks,Inc.88