Managing Arrays & Partitions
125
To return to the verification menu, press Esc. To check the progress of the array verification, you can use
the verification status described below or select Array Menu from the System Menu. The status of the
verification displays in the list of arrays.
C.2.4.1 Viewing Verification Status
You can view the status of the verification process while it is running.
To view verification status:
1 From the System Menu, select Array Menu and press Enter.
The Select Array screen displays with a list of existing arrays.
2 Select the array you want and press Enter.
The array menu displays.
3 Select Verify Function and press Enter
The verify menu displays.
4 Select View Verify Status and press Enter
The verify menu displays.
5 Press Esc to return to the verify menu.
C.2.4.2 Stopping the Verification
You can stop the verification process. Normally, you want to let the verification finish, although stopping
it does not cause any damage to your data. You may want to stop the verification if you want to improve
performance of the Galaxy 65 Subsystem for another application.