Nortel Networks 201i Network Card User Manual


 
Preparing for installation Standard 1.0
30 CallPilot
Installation overview
Introduction
This section provides a high-level overview of the requirements and
procedure for installing the 201i server.
Before you begin
Ensure that proper power and grounding are available for all the power
outlets serving the CallPilot server and its associated peripherals. Power for
these devices must be wired and fused independently of all other receptacles
and referenced to the same ground as the PBX system.
A qualified electrician must implement the single-point ground reference as
required between the power outlets of the CallPilot server and the power
outlets of the switch.
Provide a sufficient number of properly grounded power outlets or power
bars for all equipment.
For more information, refer to Chapter 2, Grounding and power
requirements, in the CallPilot Planning and Engineering Guide.