Preparing for installation Standard 1.0
34 CallPilot
9 Connect the 201i server and devices as follows:
Connect the monitor, keyboard, and mouse to the 201i
server faceplate (see page 140).
❒
Connect the CD-ROM and tape drives to the
intermediate SCSI cable (see page 142).
❒
Connect the multi I/O cable to the ELAN and CLAN
network hubs (see page 152).
Note: If more than 3 m (10 ft) of multi I/O cable is
required, use the supplied RJ-45 female-to-female
gender change jacks to attach additional cable. Up to
76.2 m (250 ft) of cable length is supported.
❒
Connect the modem to the multi I/O cable (see page
155).
❒
Connect the power cords for all devices, and then power
them up.
❒
10 Complete the installation of the 201i server as follows:
Connect the intermediate SCSI cable to the 201i server
faceplate.
Close the lock latches on the 201i server.
Boot the 201i server to Windows NT.
See page 158.
❒
11 Continue with Part 3 of the CallPilot Installation and
Configuration binder.
❒
Step Description Check