Maintenance/Replacement Menu
Please select a type of model which has FRU to be replaced.
1. BB (4s Building Block Model)
2. XBBOX (XB-BOX Model)
------------------------------------------------------------------------------
Select [1,2|c:cancel] :
c
Note
- When you incorporate a system board with the addboard command, the target system
board is incorporated into the physical partition after its hardware diagnosis. Therefore, it
may take time for the command execution to complete.
XSCF>
addboard -c configure -p 0 01-0
PSB#01-0 will be configured into PPAR-ID 0. Continue?[y|n] :
y
Start connecting PSB to PPAR. [3600sec]
0..... 30..... 60..... 90.....120.....150.....180.....210.....240.....
270.....300.....330.....360.....390.....420.....450.....480.....510.....
540.....570.....600.....630.....660.....690.....720.....750.....780.....
810.....840.....870.....900.....930.....960.....end
Connected PSB to PPAR.
Start configuring PSB to Logical Domains (LDoms) Manager. [1800sec]
0.....end
Configured PSB to Logical Domains (LDoms) Manager.
Operation has completed.
6.2 Incorporating a Chassis into a Physical
Partition
This section describes the procedure for incorporating a chassis into a physical
partition by using dynamic reconfiguration (DR) after FRU maintenance.
1.
LogintotheXSCFshell.
2.
Execute the addbo ard command to incorporate the target chassis into the
physical partition.
In response to the confirmation message, enter "y".
In the following example, PSB 01-0 is incorporated into PPAR-ID 0.
3.
Execute the sho w result command t o check th e end s t atus of the addboard
command that was just executed.
The following example shows that "0" is returned as the end status and the
execution of the addboard command has been completed successfully.
Chapter 6 Understanding the Preparations for Restoring the System 71