Connect the External Clock 5-130
Connect the Alarms 5-130
Connect the MP Connection 5-131
Connect the LAN1/2 Ports 5-132
Verify EMI Compliance 5-132
Installing the Ferrite Bead on the PXM-UI-S3/B Card 5-133
How to Install the Ferrite Bead 5-133
Installing the Ferrite Bead on Ribbon Connectors 5-135
Install the Ferrite Bead 5-135
First Time Power On Procedure for MGX Switches 5-137
Prerequisites 5-137
Tools Required 5-137
General Power On Sequence and Checkout 5-138
Specific Power On Sequence and Checkout 5-138
CHAPTER
6 Maintaining the Cisco MGX Switch or Gateway 6-1
Swapping a Primary or Redundant DC Power Entry Module with Power On 6-2
Removing and Installing the Double-Height Front Cards 6-4
Remove the Double-Height Front Cards 6-5
How Most Card Levers Work 6-5
How VXSM Card Levers Work 6-5
Install the Double-Height Front Cards 6-7
Removing and Installing the Single-Height Front Cards 6-8
Remove the Single-Height Front Cards 6-8
Install the Single-Height Front Cards 6-9
Removing and Installing the Back Cards 6-9
Remove the Back Cards 6-10
Install the Back Cards 6-11
Removing and Installing Back Card Transceivers 6-12
Remove the Back Card Transceivers 6-12
Install the Back Card Transceivers 6-13
Replacing the Air Intake Plenum Filter 6-13
Scheduled Maintenance of the Air Filter 6-14
Replacing the Filter 6-14
Removing the Center Guide Modules 6-14
Connecting the Back Cards to the APS Connector 6-17
Installing the APS Assembly in the Switch 6-19