G3vs with Intel 386 or Risc Processor to R8r
4-16Upgrade Completion
4
Upgrade Completion
Install Remaining Hardware and Administer the
System
1. If the present system was removed to make room for the Release 8r
cabinet, skip to Step 3.
2. If the Release 8r cabinet was installed while the present system is in
service, return to
‘‘Remove the Present System’’ on page 4-7
. Return to
this section when finished.
3. Connect all new and reusable I/O cables to the Release 8r cabinet.
Cross-connect at the MDF as required.
4. Remove all reusable circuit packs from the present system and install into
the Release 8r cabinet. Install any new circuit packs into the Release 8r
cabinet.
5. Install fiber optic cables and administer the fiber links as needed. Refer to
DEFINITY Enterprise Communications Server Release 8 Installation and
Test for Multicarrier Cabinets
.
6. Administer any new translations, as required.
Enable TTI
1. Type
change system-parameters features
and press Enter.
2. On the second screen, set the
Enabled?
field to
y
to activate the TTI
feature.
Check Link Status
1. Type
display communication-interface links
and press Enter. Compare it
with the earlier status.
2. Type
status link
number
and press Enter. Repeat this step for each link.
Enable Scheduled Maintenance
1. Type
change system-parameters maintenance
and press Enter. Use this
screen to enable scheduled daily maintenance.
Resolve Alarms
1. Examine the alarm log. Resolve any alarms using
DEFINITY Enterprise
Communications Server Release 8 Maintenance for R8r
.