DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115
Issue 1
April 2000
Adding or Removing Cabinet Hardware
6-21Add the Fiber Optic Cable
6
Figure 6-12. Dress the Cable
15. If a circuit pack was removed to access 2 open slots (from
‘‘Cabinet
Preparation’’ on page 6-10), replace the circuit pack into its original slot.
16. Close the front door.
17. Discard the pass-thru tool.
Test the Installation
1. Login to the management terminal.
2. Administer the system by referring to the ATM section of the
Installation
and Test for Adjuncts and Peripherals
.
3. Type
list configuration all
and press
Enter to determine if the new circuit
pack appears in the correct slot and that there are no circuit pack
conflicts.
lcda4fop RPY02139
8