DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115
Issue 1
April 2000
Multicarrier G2 Universal Module to R8r EPN
5-58High Reliability
5
For Two Collocated Expansion Port Networks
1. Behind control carrier A of PPN cabinet 1:
■ Install a lightwave transceiver on the cable connector at slot 1A02.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■ Connect a fiber optic cable to the transceiver just installed.
■ Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
2. Behind control carrier A of EPN cabinet 3:
■ Install a lightwave transceiver on the cable connector at slot 3A01.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■ Connect the other end of the fiber optic cable to the lightwave
transceiver just installed.
■ Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
■ At the top of the cabinet, coil up the surplus fiber optic cable and
attach it to the wall of the cable tray.
3. Behind control carrier A of EPN cabinet 2:
■ Install a lightwave transceiver on the cable connector at slot 2A02.
■ Connect a fiber optic cable to the transceiver just installed.
■ Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
4. Behind control carrier A of EPN cabinet 3:
■ Install a lightwave transceiver on the cable connector at slot 3A02.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■ Connect the other end of the fiber optic cable to the transceiver just
installed.
■ Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
■ At the top of the cabinet, coil up the surplus fiber optic cable and
attach it to the wall of the cable tray.