Lucent Technologies 555-233-115 Server User Manual


 
DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115
Issue 1
April 2000
Adding or Removing Cabinet Hardware
6-33Install a New EPN Cabinet in an Existing System
6
Figure 6-17. Switch-Connected Release 8r with SNC in EPN
27. Connect an H600-278 Metallic Cable from Slot 2 in the Port Carrier in
position B in Cabinet 4 (4B02) to Slot 19 on the Switch Node Carrier in
position D in Cabinet 4 (4D19).
NOTE:
Both fibers from each PN must connect to the same slot number in
each Switch Node Carrier. For example: if Slot 3A01 of EPN 3
connects to Switch Node Carrier Slot 4E19, then Slot 3B02 of EPN 3
must connect to Switch Node Carrier Slot 4D19.
28. Proceed to
Appendix A, ‘‘Fiber Link Administration’’
to add the new fiber
links.
Figure Notes:
1. Cabinet 1 (PPN)
2. Cabinet 4 (MCC EPN with One
Duplex Switch Node)
3.
Cabinet 2, 3, and 5 through 16 (MCC or SCC
EPNs)
H600-278 Metallic Cable