Lucent Technologies 555-233-115 Server User Manual


 
DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115
Issue 1
April 2000
Adding or Removing Cabinet Hardware
6-94Add a Switch Node Carrier (Standard Reliability)
6
Add a Switch Node Carrier (Standard
Reliability)
To upgrade to a standard reliability R8r with Center Stage Switch (CSS), a switch
node carrier is added either to an empty “E” carrier position of an existing
multicarrier port network or to the “D” carrier position.
NOTE:
To avoid moving a port carrier, the preferred practice is to place the new
switch node carrier in an empty carrier position.
Service Interruption
1. Since the addition of the switch node carrier requires a service
interruption, notify the customer in advance as to when the addition will
take place.
Verify System Status
1. Before proceeding, examine the system for alarms and correct all
problems. The system must be alarm-free.
Disable Alarm Origination
1. Type
change system-parameters maintenance
and press Enter.
2. Make a note of the
Alarm Origination Activated
field
administration. If the feature is enabled, type
n
in this field to disable
Alarm Origination.
!
WARNING:
If you do not disable Alarm Origination before making changes to the
switch, the switch may generate alarms, resulting in unnecessary
trouble tickets. Reducing redundant and unnecessary trouble
tickets.
NOTE:
For some releases of the software, disable
Cleared Alarm
Notification
and
Restart Notification
fields before
submitting the form.