Cisco Systems MGX 8900 Switch User Manual


 
5-50
Cisco MGX 8800/8900 Series Hardware Installation Guide
Releases 2 - 5.2, Part Number OL-4545-01, Rev. H0, May 2006
Chapter 5 Installing the Cisco MGX Switch or Gateway
Installing the MGX 8950 Switch
The MGX 8950 switch is shipped in one of two hardware configurations:
Open rack—Modules and cards are shipped preinstalled in a the Cisco MGX 8950 switch and are
tested according to customer specifications before they are shipped. The system is ready for
installation in a customer-supplied open rack. The optional AC power supply tray, air intake plenum,
upper and lower fan trays, and exhaust plenum are packaged separately and will need to be installed
in the rack.
If you are not using a mechanical lift, you will need to remove the modules and cards from the
MGX 8950 switch to lessen the weight of the chassis prior to installing it in the rack. Follow the
installation procedures in the “Rack-Mounted System (Without Lift)” column of Table 5-1.
If you are using a lift to mount the MGX 8950 switch in a rack, you do not need to remove the
modules, cards, and hardware components. Follow the installation procedures in the
“Rack-Mounted System (with Lift)” column of Table 5-1.
Cisco cabinet—All components are shipped preinstalled in a Cisco cabinet. Follow the installation
procedures in the “Cisco Cabinet System” column of Table 5-1.
Note Using a lift to install a fully loaded MGX 8950 switch in a rack greatly simplifies the installation process,
because the modules do not need to be removed from the chassis.
Before proceeding with the installation, verify that all of the ordered parts are present and in good
condition. Store a record of the parts and serial numbers. If any parts are missing or damaged, contact
your sales representative.
Caution Proper ESD protection is required whenever you handle Cisco equipment. Installation and maintenance
personnel should be properly grounded through the use of grounding straps to eliminate the risk of ESD
damage to the equipment. Modules are subject to ESD damage whenever they are removed from
the chassis.
Table 5-3 Installation Checklist—MGX 8950 System
Check Steps
Rack-Mounted System
(Without Lift) Rack-Mounted System (with Lift) Cisco Cabinet System
Step 1
Install Stability Plate for Seismic Anchoring
Step 2
Ground the Frame Bonding Ground Connection for a Cisco-Supplied Rack
Step 3
Measure Rack Space Connect the Fan Tray Power
Cables to the MGX 8950 Switch
Step 4
Connect the Fan Tray Power Cables to the MGX 8950 Switch
Step 5
Install the AC Power Supply Tray, as necessary
Remove the AC Power Supplies from the AC Power Supply Tray
Install the AC Supply Power Tray(s)
Reinstall the AC Power Supplies
Connect the DC PEM to the MGX
8950 Switch, as necessary
Step 6
Install the Air Intake Plenum Connect the Back Cards
Step 7
Install the Lower Fan Tray Connect the Console Port