Avaya P580 Switch User Manual


 
7-10 Avaya P550R, P580, P880, and P882 Multiservice Switch User Guide, v5.3.1
Chapter
WARNING
To avoid bodily harm and equipment damage, you must power
off the switch before you remove switch controllers or elements.
5. Replace the failed controller.
6. Power on the switch power supplies and login.
7. Enable the redundant hardware (see "Enabling Redundant
Hardware" earlier in this chapter).
8. Re-select Switch Fabric from the System > Configuration
group on the Web Agent window. The Switch Fabric
Status dialog box re-displays with the Switch Controller field
displaying:
# 1 Active
Replacing an Element
If an element fails, you are notified by:
An event log message
An error message that displays in the Switch Elements field
To replace a failed element:
1. Disable redundant hardware.
2. Copy the running config to the startup config.
3. Synchronize if you have redundant supervisor modules.
4. Power off the switch power supplies.
WARNING
To avoid bodily harm and equipment damage, you must power
off the switch before you remove switch controllers or elements.
5. Power on the switch power supplies and login.
6. Enable the redundant hardware (see "Enabling Redundant
Hardware" earlier in this chapter).
7. Replace the failed element.
8. Power on the switch’s power supplies and login.