Defining a T1/E1 Management Channel 158
Models 2616RC, 3096RC & 3196RC Admin Reference Guide 11 • In-band management
Example 2: T1/E1 Routed PPP Management Channel
Do the following to create a PPP channel on T1/E1 port #2, timeslots 1-2:
Figure 90. Define a T1/E1 Management Channel window, ppp(5) function selected
1. Set the parameters as follows:
Port: port2(2)
Function: ppp(5)
–Timeslots: 12
2. Click the Define button.
3. Click the In-Band Mgmt link in the Configuration Menu pane to see the newly created channel in the
Defined In-Band Management Channel table. If the PPP link does not appear, remember that the T1/E1
port must be activated before creating the in-band management channel.
Figure 91. Defined In-Band Management Channels section
Note
Since you are configuring the T1/E1 port for PPP, the timeslots will
automatically be set to PPP, even if the timeslots were previously con-
figured for clear or FrameRelay.
4. In the Protocol Type column, you will see ppp-ipcp(1) which is the default protocol (ppp-ipcp(1) is for
routed PPP channels over the T1/E1 link). The other displayed parameters are IP Address, IP Mask, and
Status.
IP Address is the IP address of the remote end of the PPP link for IPCP applications.
IP Mask is 255.255.255.255 by default. Only in rare instances would the mask not be (that is,