Installation
This section describes installing the ATM Switch Fabric Module.
Installation
Prerequisites
Before you install the ATM Switch Fabric Module, ensure that you have
met all of the following prerequisite conditions:
1
Complete the chassis unpacking and installation procedure as described
in the
Chassis Quick Installation
Guides
.
You can install the chassis in a
rack, on a shelf, or on a tabletop.
2
Install the power supply as described in the
Power Supply Installation
Guides and install the power cable as described in the
Enterprise
Management Engine Quick Start Guide for the
CoreBuilder 9000 Enterprise Switch.
3
Install the Enterprise Management Engine as described in the
Enterprise
Management Engine Quick Start Guide
for the CoreBuilder 9000
Enterprise Switch
.
4
Install the ATM Switch Fabric Module as described in the
CoreBuilder 9000 ATM Switch Fabric Module Getting Started Guide
5
Read the
CoreBuilder 9000 ATM
Interface Module Getting Started Guide
to make sure that you have all of the required components to get your
system up and running and that you have completed all of the
prerequisite work.
6
To manage the ATM Interface Module and CoreBuilder 9000 ATM
Enterprise Switch through the Simple Network Management Protocol
(SNMP), you must install the 3Com Transcend
®
Enterprise Manager for
UNIX or for Windows NT.
Installing the
Daughter Cards
For complete details on how to install the daughter cards into the ATM
Interface Module, see the
CoreBuilder 9000 ATM Interface Module
Getting Started Gu
ide.
Installing the ATM
Interface Module into
the Chassis
For complete details on how to install the ATM Interface Module into the
CoreBuilder 9000 chassis, see the
CoreBuilder 9000 ATM Interface
Module Getting Started Guide
.