Lucent Technologies R8r Server User Manual


 
DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115
Issue 1
April 2000
Multicarrier G2 Universal Module to R8r EPN
5-99Critical Reliability
5
For Either 1 or 2 Fiber-Remoted Expansion Port Networks
1. Behind control carrier A of PPN cabinet 1 (see Figure 5-33 through Figure
5-35):
Install a lightwave transceiver on the cable connector at slot 1A01.
Connect a fiber optic cable to the transceiver just installed.
Route the cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
Connect the fiber cable to the lightguide interconnect unit provided.
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
2. Behind control carrier A of EPN cabinet 2:
Install a lightwave transceiver on the cable connector at slot 2A01.
Connect the fiber optic cable to the lightwave transceiver slot 2A01.
Route the cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
Connect the fiber cable to the lightguide interconnect unit provided.
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
Coil the surplus fiber optic cable and place it in the cable manager.
3. Behind control carrier B of PPN cabinet 1:
Install a lightwave transceiver on the cable connector at slot 1B01.
Connect a fiber optic cable to the transceiver just installed.
Route the cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
Connect the fiber cable to the lightguide interconnect unit provided.
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
4. Behind port carrier B of EPN cabinet 2:
Install a lightwave transceiver on the cable connector at slot 2B02.
Connect the fiber optic cable to the transceiver just installed.
Route the cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
Connect the fiber cable to the lightguide interconnect unit provided.
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
Coil the surplus fiber optic cable and place it in the cable manager.