Adding or Removing Cabinet Hardware
6-92Add a Control Carrier (Add Duplication)
6
Relocate Port Carrier B
Refer to Add a Switch Node Carrier (High or Critical Reliability) to relocate the
removed port carrier.
Connect Management Terminal or PC
1. Behind control carrier “A,” disconnect the management terminal or PC
cable from the “TERM” connector, and reconnect the cable to the “DOT”
(duplication option terminal) connector.
Reseat DEFINITY LAN Gateway System
1. Reseat the LAN Gateway assembly into its backplane connectors.
Reseat DEFINITY AUDIX System
1. If a DEFINITY AUDIX System resides in the PPN or an EPN (where PPN
port carrier “B” was relocated), reseat the AUDIX assembly to its
backplane connectors.
Power Up System
1. At an EPN (where PPN port carrier “B” was relocated), set the main circuit
breaker to ON.
2. At the PPN, set the main circuit breaker to ON.
3. The system performs a level 4 rebooting process, loading the system
program and default or current translations from the disk. Rebooting takes
5 to 11 minutes.
NOTE:
Ignore alarms for now.
4. Type the
reset system 4
and press
Enter to copy the translations from
removable media to memory.
5. Clear any alarms.
6. Type
save translation [both]
and press
Enter if translation changes were
made in Step 8.
7. Type
restore disk [both] full
and press
Enter to copy the translations from
removable media to disk.
8. Verify that the EMERGENCY TRANSFER CONTROL switch is set to AUTO.
This restores the system to the normal operating mode.