DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115
Issue 1
April 2000
Multicarrier G2 Universal Module to R8r EPN
5-101Critical Reliability
5
5. Behind control carrier A of EPN cabinet 2:
■ Install a lightwave transceiver on the cable connector at slot 2A02.
■ Connect a fiber optic cable to the transceiver just installed.
■ Route the cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
■ Connect the fiber cable to the lightguide interconnect unit provided.
■ Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
6. Behind control carrier A of EPN cabinet 3:
■ Install a lightwave transceiver on the cable connector at slot 3A02.
■ Connect the fiber optic cable to the transceiver just installed.
■ Route the fiber cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
■ Connect the fiber cable to the lightguide interconnect unit provided.
■ Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
■ Coil up the surplus fiber cable and place it in the cable manager.
7. Behind port carrier B of EPN cabinet 2:
■ Install a lightwave transceiver on the cable connector at slot 2B03.
■ Connect a fiber optic cable to the transceiver just installed.
■ Route the fiber cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
■ Connect the fiber cable to the lightguide interconnect unit provided.
■ Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
8. Behind port carrier B of EPN cabinet 3:
■ Install a lightwave transceiver on the cable connector at slot 3B03.
■ Connect the fiber cable to the transceiver just installed.
■ Route the fiber cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
■ Connect the fiber cable to the lightguide interconnect unit provided.
■ Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
■ Coil up the surplus fiber cable and place it in the cable manager.