Access Navigator - Release 1.8 August 2003 6-39
Electrical Installation
Acceptance Test
Acceptance Test
Verification Summary
n Apply Power and Verify Operation ... 6-40
n Verify Chassis Ground Connection ... 6-41
n Verify DSX-1 Connections ... 6-41
n Verify RS-232 Management Connection ... 6-42
n Verify Ethernet Cable Connection ... 6-43
n Verify Ethernet Management Connection ... 6-43
n Verify BITS Connection ... 6-44
n Verify Alarm Output Connections ... 6-45
n Verify Alarm Input Connections ... 6-47
n Exit Management Session ... 6-48
NOTE: If connections appear to be correct but unit fails the verification requirements,
refer to Diagnostics & Troubleshooting on page 15-1.