Carrier Access Access Navigator Network Router User Manual


 
Access Navigator - Release 1.8 August 2003 5-15
Physical Installation
Vertical Wall Mount
Vertical Wall Mount
NOTE: The following procedure assumes that the Access Navigator and other compo-
nents will be mounted on a plywood sheet before attaching plywood to wall. Pre-mounting
equipment at the carrier facility will speed up installation at the customer site.
Installation Summary
n Precautions ... 5-15
n Tools and Materials ... 5-16
n Ensure Adequate Clearance ... 5-16
n Prepare Plywood ... 5-16
n Attach Mounting Brackets to Access Navigator ... 5-16
n Attach Mounting Brackets to Access Navigator ... 5-16
n Attach Access Navigator to Plywood ... 5-17
Precautions
CAUTION! WALL MOUNTING IS APPROVED ONLY FOR CUSTOMER PREMISES.
CAUTION! ACCESS NAVIGATOR REQUIRES FREE AIR SPACE ON TOP, BOTTOM, AND
ENDS OF CHASSIS FOR AIR CIRCULATION. INSUFFICIENT VENTILATION MAY CAUSE
SERVICE INTERRUPTIONS, RESULTING FROM EQUIPMENT OVERHEATING AND SHUTTING
DOWN. DO NOT ALLOW CABLES AND OTHER COMPONENTS TO OBSTRUCT AIR
CIRCULATION. THE ACCESS NAVIGATOR INCLUDES TIE POINTS FOR ATTACHING WIRE
TIES TO SECURE CABLES TO REAR PANEL WITHOUT OBSTRUCTING AIR FLOW (SEE
FIGURE 5-11).
WARNING! IF ACCESS NAVIGATOR IS MOUNTED ON PLYWOOD, DO NOT USE A
HAMMER TO ATTACH PLYWOOD TO WALL BECAUSE THE IMPACT SHOCK MAY DAMAGE
THE ACCESS NAVIGATOR AND OTHER COMPONENTS MOUNTED ON THE PLYWOOD. A
POWER DRILL AND SCREWDRIVER IS RECOMMENDED TO AVOID DAMAGE.