DEFINITY Enterprise Communications Server Release 6
Maintenance for R6vs/si
555-230-127
Issue 1
August 1997
Maintenance Object Repair Procedures
Page 10-597ETR-PT (Enhanced Tone Receiver Port)
10
Table 10-206. TEST #43 Tone Detector Audit/Update Test
Error
Code
Test
Result Description/ Recommendation
none ABORT The system was not able to allocate all the resources needed for this test.
1. Wait 1 minute, and repeat the command a maximum of 5 times.
2000 ABORT Response to the test request was not received within the allowable time
period.
2100 ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals a maximum of 5 times.
2. If the test continues to abort, escalate the problem.
FAIL Hardware audit failed.
1. Run the short test sequence via the test port PCSSpp sh r 1
command.
2. If the problem persists, the system is still operating properly but system
capacity will be reduced. In order to restore system performance to
normal, replace the circuit pack containing the defective ETR-PT.
Follow the procedures described in the TONE-BD section for replacing
a tone/clock circuit pack.
PASS The ETR Port has passed the sanity inquiry.
Continued on next page