Maintenance Object Repair Procedures
Page 10-807MET-LINE (MET Line)
10
System Technician-Demanded Tests:
Descriptions and Error Codes
Always investigate tests in the order presented in the table below when
inspecting errors in the system. By clearing error codes associated with the
Port
Diagnostic Test,
for example, you may also clear errors generated from other
tests in the testing sequence.
For example, you may also clear errors generated from other tests in the testing
sequence.
NPE Crosstalk Test (#6)
One or more NPEs reside on each circuit pack with a TDM Bus interface. The
NPE controls port connectivity and gain, and provides conferencing functions on
a per port basis. The NPE Crosstalk Test verifies that this port’s NPE channel
talks on the selected time slot and never crosses over to time slots reserved for
other connections. If the NPE is not working correctly, one-way and noisy
connections may be observed. This test is part of a port’s Long Test Sequence
and takes about 20 to 30 seconds to complete.
1. D = Destructive; ND = Nondestructive
Order of Investigation
Short Test
Sequence
Long Test
Sequence D/ND
1
NPE Crosstalk Test (#6) X ND
Port Diagnostic Test (#35) X ND
MFAT Electronic Power Feed Test (#56) X ND
Hybrid Circuit and Conference Circuit Test (#57) X ND
Station Lamp Update Test (#60) X X ND
Station Audits Test (#61) X X ND
Ringer Update Test (#62) X X ND
Table 10-271. TEST #6 NPE Crosstalk Test
Error
Code
Test
Result Description/ Recommendation
ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at one-minute intervals a maximum of five times.
2. If the test continues to abort, escalate the problem.