DEFINITY Enterprise Communications Server Release 6
Maintenance for R6vs/si
555-230-127
Issue 1
August 1997
Maintenance Object Repair Procedures
Page 10-914PDMODULE, TDMODULE (Data Module)
10
tested after the primary data module. If either test fails, both data modules are
taken out of service This test usually runs only during the Long Test Sequence
and takes about 20 to 30 seconds to complete.
Table 10-307. TEST #9 NPE Crosstalk Test
Error
Code
Test
Result Description/ Recommendation
1 ABORT During testing of the primary information channel, system resources
may not have been available.
1. Check the port status. Use the display port PCSSpp command
to determine the station extension of the port. Use the station
status command to determine the service state of the port. If the
service state indicates that the port is in use, then the port is
unavailable for this test. You must wait until the port is idle.
2. If the port status is idle, then retry the command at one-minute
intervals a maximum of five times.
3. If the test continues to abort, escalate the problem.
1000 ABORT System resources required to run this test are not available. The port
may be busy with a valid call. Use the display port PCSSpp
command to determine the extension of the data module port. Use
the status data-module command to determine the service state of
the port. If the service state indicates that the port is in use, then the
port is unavailable for certain tests. (Refer to the "Status Commands"
section in Chapter 8, ‘‘
Maintenance Commands and
Trouble-Clearing Aids’’ for a full description of all possible states).
You must wait until the port is idle before retesting.
1. If the port status is idle, retry the command at one-minute
intervals a maximum of five times.
2. If the test continues to abort, escalate the problem.
1001 ABORT System resources to run this test are not available.
1. Retry the command at one-minute intervals a maximum of five
times.
2. If the test continues to abort, escalate the problem.
Continued on next page