DEFINITY Enterprise Communications Server Release 6
Maintenance for R6vs/si
555-230-127
Issue 1
August 1997
Maintenance Object Repair Procedures
Page 10-1372TIE-TRK (Tie Trunk)
10
System Technician-Demanded Tests:
Descriptions and Error Codes
Always investigate tests in the order presented in the table below when
inspecting errors in the system. By clearing error codes associated with the
Loop
Around and Conference Circuit Test,
for example, you may also clear errors
generated from other tests in the testing sequence.
Notes:
a. ATMS test are not part of either sequence. They are run either on demand
with the test analog-testcall command or via the ATMS schedule.
NPE Crosstalk Test (#6)
One or more NPE reside on each circuit pack with a TDM Bus interface. The NPE
controls port connectivity and gain, and provides conferencing functions on a
per port basis. The NPE Crosstalk Test verifies that this port’s NPE channel talks
on the selected time slot and never crosses over to time slots reserved for other
connections. If the NPE is not working correctly, one-way and noisy connections
may be observed. This test is usually only part of a port’s Long Test Sequence
and takes 20 to 30 seconds to complete.
1. D = Destructive; ND = Nondestructive
2. Non-TN439 and non-TN497 circuit packs only
3. TN439 circuit pack only
4. TN497 circuit pack only
5. G3iV1.1-286 and G3iV2-386 only
6. Non-TN497 circuit packs only
Order of Investigation
Short Test
Sequence
Long Test
Sequence D/ND
1
NPE Crosstalk Test (#6) X ND
Loop Around and Conference Circuit Test
(#33)
XND
Tie Trunk Seizure Test (#73)(
2
), Tie Trunk
Dial Test (#747)(
3
), Seizure Test (#73)(
4
)
XXND
Tie Trunk EPF Test (#74)(
5
)XXND
Port Audit and Update Test (#36)(
6
), Audit
and Update Test (#36)(
4
)
XXND
Analog Transmission Test (#844-848) (a) (a)