Lucent Technologies lucent Server User Manual


  Open as PDF
of 2392
 
DEFINITY Enterprise Communications Server Release 6
Maintenance for R6vs/si
555-230-127
Issue 1
August 1997
Maintenance Object Repair Procedures
Page 10-1385TIE-TRK (Tie Trunk)
10
1040 ABORT This test is not performed for trunk ports administered as "access
endpoints."
1. Verify this port is an access endpoint by using the display port
command.
2. If the port has been administered as an access endpoint, this test
should abort.
2000 ABORT Response to the test request was not received within the allowable time
period.
2100 ABORT Could not allocate the necessary system resources to run the test. This
could be due to a failure to seize the port.
1. Retry the command at 1-minute intervals a maximum of 5 times.
2. If the test continues to abort, escalate the problem.
1 FAIL The E lead test failed due to an on-board port problem.
1. Replace the circuit pack.
2 FAIL The M lead test failed. The EPF has experienced an overcurrent condition,
perhaps due to the external M lead.
1. To make sure the problem is on-board, disconnect the facility from the
pack and retry the test.
2. If the test fails, replace the circuit pack. Otherwise, check the external
wiring toward the far-end PBX.
PASS Tie Trunk EPF test is successful. This port is functioning properly.
1. If users are reporting troubles, examine loop connections to the port.
0NO
BOARD
The test could not relate the internal ID to the port (no board).
1. Check to ensure that the board translations are correct. Translate the
board, if necessary.
2. Issue the busyout board command.
3. Issue the reset board command.
4. Issue the release busy board command.
5. Issue the test board command. This should re-establish the linkage
between the internal ID and the port.
Table 10-480. TEST #74 Tie Trunk EPF Test — Continued
Error
Code
Test
Result Description/ Recommendation
Continued on next page