Lucent Technologies lucent Server User Manual


  Open as PDF
of 2392
 
DEFINITY Enterprise Communications Server Release 6
Maintenance for R6vs/si
555-230-127
Issue 1
August 1997
Maintenance Object Repair Procedures
Page 10-1564XXX-BD (Common Port Circuit Pack)
10
Neon Test (#220)
This test checks the voltage required to light the neon lamp on an analog
terminal. A relay connects a 150V DC source from the backplane of the circuit
pack onto the voltage bus, and another relay connects a 2K shunt from the bus
to ground. Current in the line is then monitored to determine if the voltage is
present.
The neon test runs only for TN746 and TN769 Analog circuit packs. If the circuit
pack is not a TN746 or TN769, the test returns PASS, but there is no testing done
to the circuit pack.
Table 10-530. TEST #220 Neon Test
Error
Code
Test
Result Description/ Recommendation
1004 ABORT The port was seized by a valid call during the test. The test has been
aborted. Use the display port PCSSpp command to determine the station
extension. Use the status station command to determine the service state
of the port. If the service state indicates that the port is in use, then the port
is unavailable for certain tests. (Refer to the "Status Commands" section in
Chapter 8, ‘‘
Maintenance Commands and Trouble-Clearing Aids’’ for a full
description of all possible states.) You must wait until the port is idle before
retesting.
1. Retry the command at one-minute intervals a maximum of five times.
2. If the test continues to abort, escalate the problem.
1008 ABORT Could not allocate a ringing circuit. Either all the ringing circuits are in use,
or the ringing generator is defective or is not wired correctly.
1. Retry the command at one-minute intervals a maximum of five times.
2. If the test continues to abort, look for RING-GEN errors in the Error
Log. If an ABORT 1008 occurs for this test on other circuit packs as
well, then the ringing generator may be defective or is not wired
correctly (see errors for RING-GEN). If it doesn’t occur on port test 48
for ANL-16-L, then all four ring phases are in use.
3. If the test to continues to abort, escalate the problem.
Continued on next page