Maintenance Object Repair Procedures
Page 10-873M/T-ANL (Maintenance/Test Analog Port)
10
Analog Port Sanity Test (#963)
This test verifies that the port circuitry involved in the analog trunk testing on the
Maintenance/Test Analog Port is functioning properly.
This test will abort if an ATMS Test Call is in progress on the Maintenance/Test
Analog Port when the test is requested.
Table 10-294. TEST #566 Hook State Inquiry
Error
Code Test Result Description/ Recommendation
1 ABORT Switch hook audit timed out. No response was received from the
circuit pack for information about the switch hook state.
1. Retry the command at 1 minute intervals a maximum of 3 times.
2. If the test continues to abort, replace the circuit pack and repeat
the test.
3. If the test continues to abort, escalate the problem.
2100 ABORT System resources required to run this test are not available.
1. Retry the command at 1 minute intervals a maximum of 3 times.
2. If the test continues to abort, escalate the problem.
Any FAIL Internal System Error
1. Retry the command at 1 minute intervals a maximum of 3 times.
2. If the test continues to fail reset the circuit pack via the busyout
board PCSS, reset board PCSS, release board PCSS
command sequence.
3. Retry the command at 1 minute intervals a maximum of 3 times.
4. If the test continues to fail, escalate the problem.
PASS Call processing and Maintenance/Test Analog Port maintenance
software agree on the Maintenance/Test Analog Port hook state.
Continued on next page