Lucent Technologies lucent Server User Manual


  Open as PDF
of 2392
 
DEFINITY Enterprise Communications Server Release 6
Maintenance for R6vs/si
555-230-127
Issue 1
August 1997
Maintenance Object Repair Procedures
Page 10-812MET-LINE (MET Line)
10
1004 ABORT The port was seized by a valid call during the test. The test has
been aborted. Use the display port PCSSpp command to
determine the station extension of the port. Use the status
station command to determine the service state of the port. If
the service state indicates that the port is in use, then the port is
unavailable for certain tests. (See Chapter 8, ‘‘
Maintenance
Commands and Trouble-Clearing Aids’’, for a full description of
all possible states.) You must wait until the port is idle before
retesting.
NOTE:
The battery feed circuitry is tested for proper battery
voltage by testing the switchhook state. In response to the
test message, the on-board firmware terminates the line
and checks for switch-hook presence. The termination is
then removed, and a check is made for no switch-hook
presence. The MET set must be on-hook for the test to
execute.
1. If the port status is idle, then retry the command at 1-minute
intervals a maximum of 5 times.
2. If the test continues to abort and the port is not in use,
escalate the problem.
1018 ABORT Test disabled via software patch.
1. Escalate to next tier level.
2000 ABORT This port may have been busied out by system technician.
1. Look in the Error Log for Error Type 18 (port busied out) for
this port. If this error type is present, then release the port
via the release station <extension> command and run the
test again.
2. Make sure that the terminal is connected.
3. Retry the command at one-minute intervals a maximum of
five times.
4. If the test continues to abort, escalate the problem.
Table 10-272. TEST #35 Port Diagnostic Test — Continued
Error
Code
Test
Result Description/ Recommendation
Continued on next page