DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page 10-524DIOD-TRK (DIOD Trunk) [G1.2SE]
10
Table 10-142. TEST #33 Loop Around and Conference
Circuit Test
Error
Code
Test
Result Description/ Recommendation
ABORT Could not allocate system resources to run this test.
7 ABORT Conference Circuit Test aborted.
1000 ABORT System resources required to run this test are not available.
The port may be busy with a valid call. Use the display port
PCSSpp command to determine the trunk group/member
number of the port. Use the status trunk command to
determine the service state of the port. If the service state
indicates that the port is in use, then the port is unavailable
for certain tests. (Refer to the "Status Commands" section in
Chapter 10, "Maintenance Commands and
Trouble-Clearing Aids" for a full description of all possible
states.) You must wait until the port is idle before retesting.
1. If the port status is idle, then retry the command at
one-minute intervals a maximum of five times.
2. If the test continues to abort, escalate the problem.
1004 ABORT The port has been seized by a user for a valid call. Use the
status trunk command to determine when the port is
available for testing.
1. Retry the command at one-minute intervals a maximum
of five times.
2. If the test continues to abort and the port is not in use,
escalate the problem.
2100 ABORT Could not allocate the necessary system resources to run
this test.
1. Retry the command at one-minute intervals a maximum
of five times.
2. If the test continues to abort, escalate the problem.
Continued on next page