DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page 10-985OPS-LINE (DS1 OPS Line)
10
System Technician-Demanded Tests:
Descriptions and Error Codes
Always investigate tests in the order presented in the table below when
inspecting errors in the system. By clearing error codes associated with the
NPE
Crosstalk Test,
for example, you may also clear errors generated from other tests
in the testing sequence.
NPE Crosstalk Test (#6)
One or more NPEs reside on each circuit pack with a TDM Bus interface. The
NPE controls port connectivity and gain, and provides conferencing functions on
a per-port basis The NPE Crosstalk Test verifies that this port’s NPE channel talks
on the selected time slot and never crosses over to time slots reserved for other
connections. If the NPE is not working correctly, one-way and noisy connections
may be observed. This test is usually only part of a port’s Long Test Sequence
and takes about 20 to 30 seconds to complete.
1. D = Destructive; ND = Nondestructive
Order of Investigation
Short Test
Sequence
Long Test
Sequence D/ND
1
NPE Crosstalk Test (#6) X ND
Conference Circuit Test (#7) X ND
DS1OPS Switchhook Inquiry Test (#312) X X ND
Audit and Update Test (#36) X X ND
Table 10-285. TEST #6 NPE Crosstalk Test
Error
Code
Test
Result Description/ Recommendation
ABORT Could not allocate system resources to run this test or
an internal system error (software) occurred.
1. Retry the command at 1-minute intervals a maximum
of 5 times.
2. If the test continues to abort, escalate the problem.
Continued on next page