DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page 10-1315SW-CTL (Switch Control)
10
Notes:
a. Refer to DATA-BD (Network Control Circuit Pack) Maintenance
documentation for a description of these tests.
b. Refer to DATA-CHL (Network Control Channel) Maintenance
documentation for a description of these tests.
Control Channel Interface Test (#92)
Loop back messages are sent to the Switch Control via the interface used for
control channel messages. The messages are returned to the SPE for verification
via the same interface.
Table 10-396. TEST #92 Control Channel Interface Test
Error
Code
Test
Result Description/ Recommendation
2012 ABORT Internal system error
2013
2100
none
ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals a maximum of 5 times.
1029
2014
2015
2016
2017
2018
2020
2022
2024
2025
2051
ABORT Refer to STBY-SPE for a description of these error codes.
Continued on next page