DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page 10-10AC-POWER
10
Error Log Entries and Test to Clear Values
Refer to the appropriate test description and follow the recommended
procedures.
AC Power Query Test (#78)
1. Run the Short Test Sequence first. If all tests pass, run the Long Test Sequence.
Table 10-3. AC Power Error Log Entries
Error
Type
Aux
Data Associated Test
Alarm
Level
On/Off
Board Test to Clear Value
0
1
0 Any Any Any test environment P sh r 1
513 Any AC Power Query
Test (#78)
WARNING OFF test environment P sh r 1
Table 10-4. TEST #78 AC Power Query Test
Error
Code
Test
Result Description / Recommendation
1000 ABORT System resources required to run this test are not available.
1. Retry the command at 1-minute intervals a maximum of 5 times.
2000 ABORT Response to the test request was not received within the allowable time
period.
1. Retry the command at 1-minute intervals a maximum of 5 times.
2. If the test continues to ABORT with Error Code 2000, check for system
powering problems with the A carrier (PPN or EPN). Resolve all
DC-POWER alarms. Then, repeat the test.
3. If the test continues to ABORT with a 2000 Error Code, resolve all
DUPINT (Duplication Interface) errors in a high or critical reliability
system PPN, PR-MAINT (Maintenance/Tape Processor) errors in a
standard PPN, or MAINT (EPN Maintenance circuit pack) errors in an
EPN. Repeat the test.
2029 ABORT Internal system error
1. Retry the command at 1-minute intervals a maximum of 5 times.
Continued on next page