DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page 10-762HYB-LINE (Hybrid Line)
10
Hybrid Line Audits Test (#61)
This is a series of three tests that are classified as audits. These audits abort if
attempted on an out-of-service station. The tests are as follows:
■ Switchhook Audit - This is an update of the SPE records according to the
circuit packs’ records.
■ Bad Scan Inquiry - A message is sent uplink that contains a count that is
generated due to certain events relating to the data link conditions. This is
an indication of data transmission problems between the Hybrid circuit
pack and the voice terminal.
■ EPF Inquiry - The status of the Electronic Power Feed is sent uplink.
Possible conditions are: EPF-on-ok, EPF-off, EPF-no-load, and
EPF-on-overcurrent.
0NO
BOARD
The test could not relate the internal ID to the port (no
board). This could be due to incorrect translations, no
board is inserted, an incorrect board is inserted, or an
insane board is inserted.
1. Check to ensure that the board translations are
correct. Use the list config command, and resolve
any problems that are found.
2. If the board was found to be correctly inserted in
step 1, issue the busyout board command.
3. Issue the reset board command.
4. Issue the release busy board command.
5. Issue the test board long command. This should
re-establish the linkage between the internal ID and
the port. If this is not the case, dispatch to check to
ensure that there is a valid board inserted.
Table 10-212. TEST #60 Hybrid Line Lamp Updates Test — Continued
Error
Code
Test
Result Description/ Recommendation
Continued on next page