DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page 10-56ANL-16-L (16-Port Neon Analog Line)
10
Station Present Test (also called Ringing
Application Test) (#48)
This test provides a burst of ringing current to the terminal equipment and
detects that current flows. This test ascertains whether terminal equipment is
connected to the port.
1 FAIL This does not indicate a hardware problem. The switchhook audit failed.
The other updates were not performed because of this failure. This may
occur when the audit is performed at the same time that the terminal
equipment goes off-hook. Use the status station command to determine
when the port is available for testing.
1. When the port becomes available for testing, retry the command at
one-minute intervals a maximum of five times.
5 FAIL This does not indicate a hardware problem. However, there may be an
internal software error. The message waiting lamp update failed. The
translation and ringer updates were not performed because of this failure.
7 FAIL The translation update failed. This does not indicate a hardware problem.
However, there may be an internal software error. The ringer update was
not performed because of this failure.
8 FAIL This does not indicate a hardware problem. However, there may be an
internal software error. The ringer update failed.
1. Retry the command at one-minute intervals a maximum of five times.
PASS The software and the port processor have the same status. User-reported
troubles on this port should be investigated by using other port tests, by
examining station wiring, or by examining the station.
0NO
BOARD
The test could not relate the internal ID to the port (no board). This could
be due to incorrect translations, no board is inserted, an incorrect board is
inserted, or an insane board is inserted.
1. Check to ensure that the board translations are correct. Use the list
config command, and resolve any problems that are found.
2. If the board was found to be correctly inserted in step 1, issue the
busyout board command.
3. Issue the reset board command.
4. Issue the release busy board command.
5. Issue the test board long command. This should re-establish the
linkage between the internal ID and the port. If this is not the case,
dispatch to check to ensure that there is a valid board inserted.
Table 10-23. TEST #36 Station Status and Translation Audits and Updates Test — Continued