Maintenance Commands and Trouble-Clearing Aids
Page 8-386status audits
8
Feature Interactions
The data displayed by "status audits cumulative" and "status audits peak-hour"
can be affected by the "clear audits" command. The "clear audits cumulative"
command clears the data collected to date and resets the start time kept for that
data and also clears the peak hour’s data. The "clear audits peak-hour"
command clears the data kept for the peak hour so that a new peak hour can be
established.
When the "schedule" option is specified, the command is validated and then a
scheduling form is displayed to allow the technician to schedule execution of the
command. Refer to the Report Scheduler and System Printer feature
specification [3] for details about the scheduling form.
TABLE OF AUDITS
The following table shows the names of the audits that are run as part of time
available maintenance, the audit number (pname) and a short description of
each audit. These audits are executed using lname MO_DR_AUDIT (8192).
These audits may be executed using the
test MO
command with lname 8192,
pname "audit number," and test number 0 (for example,
test MO l 8192 p 607 t 0
will execute the AC state audit).
Audit Name
Audit
Number Description
AC-ISG 607 AC state audit
ADJUSR 595 Adjunct user record audit
ADMTRM 559 Administration terminal audit
ANUR-A 589 Announcement user record audit
AN-ADM 574 Announcement group administration audit
AN-CALLS 572 Announcement group calls audit
AN-QUE 577 Announcement group queue audit
AQSA 545 ACB queue slot allocation audit
ASLINK 606 ASAI link status audit
ASYLED 605 ASAI yellow LED audit
ATACT 558 Attendant active audit
ATAV 557 Attendant availability audit
ATDRCNT 576 Attendant resource count audit
AT-ADM 529 Attendant group administration audit