DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page 10-526DIOD-TRK (DIOD Trunk) [G1.2SE]
10
Table 10-143. TEST #36 Port Audit Update Test
Error
Code
Test
Result Description/ Recommendation
ABORT Could not allocate the necessary system resources to
run this test.
1. Retry the command at one-minute intervals a
maximum of five times.
2. If the test continues to abort, escalate the problem.
2100 ABORT Could not allocate the necessary system resources to
run the test.
FAIL Internal System Error.
1. Retry the command at one-minute intervals a
maximum of five times.
2. If test continues to fail, escalate the problem.
PASS This test passed. Translation information was
successfully updated on the circuit pack. User-reported
troubles on this port should be investigated by using
other port tests and by examining trunk or external
wiring. If the trunk is busied out, the test does not run,
but returns PASS. To verify that the trunk is in-service:
1. Enter status-command to verify that the trunk is
in-service. If the trunk is in-service, no further action
is necessary. If the trunk is out-of-service, continue
to Step 2.
2. Enter release-trunk command to put trunk back into
in-service.
3. Retry the test command.
Continued on next page