DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page 10-1223S-SYN-PT (Speech Synthesis Port)
10
Speech Synthesis PSS Handshake Test (#168)
This test verifies control functionality between the on-board microprocessor and
PSS controller. A failure occurs if either of the following events occur:
The on-board microprocessor times out while waiting for the PSS
controller to respond.
An invalid command is received by the on-board microprocessor from the
PSS controller.
This type of failure affects all four ports on the Speech Synthesis circuit pack,
resulting in errors or alarms on each port.
1000 ABORT System resources required to run this test are not
available. The port may be busy with a valid call and
therefore unavailable for certain tests. You must wait
until the port is idle (yellow LED if off) before retesting.
1. If the port is idle, retry the command at one-minute
intervals a maximum of five times.
2. If the test continues to abort, escalate the problem.
2000 ABORT Response to the test request was not received within the
allowable time period.
2100 ABORT Could not allocate the necessary system resources to
run this test.
1. Retry the command at one-minute intervals a
maximum of five times.
2. If the test continues to abort, escalate the problem.
Any FAIL The SSD is insane.
1. Replace the circuit pack.
PASS The SSD is sane. User-reported troubles should be
investigated using other tests and verifying other ports
on this circuit pack are working correctly.
Table 10-380. TEST #167 Speech Synthesis SSD Inquiry Test — Continued
Error
Code
Test
Result Description/ Recommendation
Continued on next page