DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Reliability Systems: A Maintenance Aid
Page 6-25Repair Procedures for High and Critical Reliability
6
recover the translations when the Active SPE enables memory
shadowing to the Standby SPE.
e. At the prompt REPLACE TRANSLATION MEM-CARD ON
<ACTIVE SPE> WITH SOFTWARE MEM-CARD, wait 3 minutes for
the Standby SPE to initialize before proceeding to next step.
f. Issue the list configuration software-versions long command to
ensure that both SPEs are running identical software. Use the next
step if the this command does not display the software versions,
otherwise skip the next step.
g. Issue the busyout spe-standby command followed by the release
spe-standby command to force the Standby SPE into a mode to
accept the list configuration software-versions long command.
Wait 5 minutes for the Standby SPE to initialize and issue the status
system 1st-cabinet command. The Standby SPE failed to initialize
if the Standby SPE Mode is down. If the Standby SPE Mode is
maint/init or maint/entering, execute the busyout spe-standby
and release spe-standby command up to 2 more times. If this step
does not succeed, try this procedure again.
7. Issue the status system 1st-cabinet command. The status system form
indicates the presence of MAJOR and MINOR alarms on both SPEs. If
SPE alarm counts are displayed, run component tests to resolve these
alarms. Allowed tests include test spe-standby, test duplication-
interface, and test shadow-link. Use the next step if the allowed test
commands are not accepted, otherwise skip the next step.
!
CAUTION:
If the Duplication Interface circuit pack is being tested, Test #278
fails because the SPE Select Switches are thrown.
8. Issue the busyout spe-standby command followed by the release
spe-standby command to force the Standby SPE into a mode to accept
the test commands attempted in the previous step. Wait 5 minutes for the
Standby SPE to initialize and issue the status system 1st-cabinet
command. If the Standby SPE failed to initialize if the Standby SPE Mode
is down. If the Standby SPE Mode is maint/init or maint/entering,
execute the busyout spe-standby and release spe-standby command
up to 2 more times. If this step does not succeed, try this procedure again.
9. If other Standby SPE circuit packs are to be replaced, return to Step 2.
10. Move each SPE Select Switch back to the AUTO position. If any of the
TN777B Network Control or the Processor circuit packs were replaced,
please refer to the ‘‘
Additional Tests for Replaced DATA-CHL, PKT-CTRL,
and PROCR Circuit Packs’’ section.